SAP → 1C: five risks that need to be assessed before migration

The SAP → 1C migration fails not because of the platform itself, but because of the attempt to migrate the system as a set of screens without understanding the business logic.

Hero-picture for the page “SAP → 1C: five risks that need to be assessed before migration”

Five decisions before the start

What we save

Which SAP business logic is really needed and which should be rethought in the target Russian ERP environment.

What data do we transfer?

History, balances, contracts, master data, documents, analytics, archive and reconciliation rules.

How to close reports

Financial, management, regulatory and operational reporting should be designed before migration.

How we change processes

Users need to understand the new experience, not just the new interface.

What do we use to divide into stages

By what boundaries is the transition divided—environment, legal entity, accounting unit—and what constitutes successful completion of each stage.

Five risks: indicator, consequence, measure

A risk map is useful when, for each item, it’s clear how it’s detected before launch, what consequences it has on the project, and what actions are taken to address it. Below are five risks that most often determine the outcome of a migration.

RiskHow to recognize in advanceWhat it leads toWhat to do
Underestimation of integrationsThere is no complete list of exchanges: banks, EDI, DWH and BI, portals, warehouse and production; some exchanges rely on scripts with no owner.Exchanges surface during the testing phase, deadlines slip, and some operations are handled manually for a period of time.Inventory of integrations with owner and traffic volume for each; the integration environment is designed in parallel with the functional one, not after it
Loss of informal logicKey calculations reside in modifications that no one has documented; only one person can answer the question “why is it calculated this way.”After the transition, the amounts diverge, and there's nothing to restore the original rule from.Reviewing enhancements with business owners prior to design, documenting rules in requirements, acceptance tests based on historical examples
Dirty reference dataDuplicate counterparties and nomenclature, unfilled mandatory attributes, inconsistent classifiers across different modulesData migration multiplies errors, reporting doesn't balance, and users don't trust the new systemCleaning and deduplication before migration, master data management rules and responsible persons, automatic quality checks on upload
Late-stage design of reporting and control proceduresReporting is discussed after the core functions are launched; the list of mandatory forms and controls has not been compiled.The first period closing is done manually, regulatory forms are compiled in tables, increasing the risk of errors in reportingList of mandatory reports and controls—at project inception; test period closing prior to transition to production
Lack of a phased transition planThe plan looks like a "big bang migration"; there is no pilot area, acceptance criteria, or rollback scenario.Any issue at the start halts the entire operational work, with no fallback option.Phased rollout by contours or legal entities, pilot on a limited scope, acceptance criteria and rollback plan for each phase

Where to start

Analyzing these five risks within a specific landscape is the subject of a brief assessment, not a multi-month pre-project phase. Next comes the migration program: target architecture, data migration, reconciliation, cutover, and support.

Let's discuss your environment

Describe the task, current systems, constraints, and expected results. We will offer a practical first step: diagnostics, pilot, audit, roadmap or project team.

Contact us
AI assistant
Hello! I am an AI assistant at RESTART. I’ll help you find the right section of the site, answer questions about services, licenses, partnerships, contacts, or formulate an appeal to the sales department.